GTG & HRSG Unit - Ex Coryton Oil Refinery

Started: 04 September 2015 at 09:00 BST
Ended: 29 March 2017 at 11:00 BST
GEC Alsthom 28.3MW Gas Turbine Generator Unit and Heat Recovery Steam Generator Available by Private Treaty
  •  site
    LOT 1
    GEC Alsthom 28.3MW Gas Turbine Generator Unit and Heat Recovery Steam Generator
    Commissioned 1995. GT Unit design capacity 28.3MW. HRSG Unit design capacity: 136 tonnes/hour of HP steam (42.4 barg, 400 ˚C) + 11.4 t/h of MP steam (8.6 barg, 181 ˚C)
    Sale has ended